Commissioning of 90 m3 well kiln of Shanxi Zhongda Aluminum Industry Co. Ltd Succeeds With A Single Operation. |
Source: Author: Date£º2014-1-14 Clicks£º1724 |
90m3 well kiln of Shanxi Zhongda aluminum industry co. ltd designed, constructed and contracted by our company commenced to construct in July 2013 ,and completed on 15 October 2013. It ignited to dry the kiln on 19 October 2013. The ignition and commissioning succeed with a single operation. Xian Hengxin kiln technology Co.Ltd 10. January 2014
|